This information outlines the traffic management arrangements for a temporary footway closure along Severnside Footway, Ironbridge.

Taziker Industrial on behalf of The Ironbridge Conservation Project are planning to undertake Bridge Refurbishment Works. The work is set to commence on Monday 11th September 2017 and will last for a duration of 416 days with an end date of Wednesday 31st October 2018.

The following footways are affected: the footway from side of Toll House, along one side of The Ironbridge and Severnside Footway from Tontine Hill under the bridge to the steps to the memorial. The diversion route for pedestrians will be signed on site.